₹300.00 Original price was: ₹300.00.₹200.00Current price is: ₹200.00.
Highest Motor Rating = 200 kW
Total Load =
Full Load Current of Highest Motor = kW/(1.732*V*pf*eff)
= 200*1000/ (1.732*380*0.80*0.90)
= 422.05 Amps
Startup current = 4 * Full Load Current (Soft Starter)
= 4 * 422.05
= 1688.21 Amps
Start up power of Highest Motor = (1.732*1688.21*380)/1000
= 1111.11 kVA
Notes:
This document has been exclusively prepared by SENEDS. SENEDS will not be responsible for any discrepancies or errors found within the document. Once the document is purchased payments are non-refundable.
For any queries or clarifications, we kindly request that you refrain from calling or emailing us.
₹300.00 Original price was: ₹300.00.₹200.00Current price is: ₹200.00.
Highest Motor Rating = 200 kW
Total Load =
Full Load Current of Highest Motor = kW/(1.732*V*pf*eff)
= 200*1000/ (1.732*380*0.80*0.90)
= 422.05 Amps
Startup current = 4 * Full Load Current (Soft Starter)
= 4 * 422.05
= 1688.21 Amps
Start up power of Highest Motor = (1.732*1688.21*380)/1000
= 1111.11 kVA
SEN EDS offers Engineering Consultancy, Detailed Engineering Services and Power System Engineering Services (ETAP & DIgSILENT) for Switchyard up to 400kV Substation, Port, Industrial Project (Oil and Gas Plant, Steel Plant, Thermal Power Plant, Cement Plant, Water Treatment Plant), Grid Impact Study and Grid Code Compliance (UK, Oman, KSA, UAE, etc.), Airport Project, Specializing in Renewable Energy (Solar and Wind with BESS Plant)